Line 1: Line 1:
 ====== Completing Timesheets - hints for problems ====== ====== Completing Timesheets - hints for problems ======
 +
  
 ===== Shifts not for correct time ===== ===== Shifts not for correct time =====
Line 39: Line 40:
 ===== No Units in the Pay Lines ===== ===== No Units in the Pay Lines =====
 There is a mismatch between the Rates Scheme and the Candidate match it is looking for - usually the Candidate's Grade. There is a mismatch between the Rates Scheme and the Candidate match it is looking for - usually the Candidate's Grade.
-Perhaps the Candidate has not been coded to hve the grade - inform Compliance to set code the candidate's skills and then the match will happen. +Perhaps the Candidate has not been coded to have the grade - inform Compliance to set code the candidate's skills and then the match will happen. 
 Or perhaps the Scheme does not have lines that cover the grade - inform the Section Manager to correct the scheme and then the match will happen. Or perhaps the Scheme does not have lines that cover the grade - inform the Section Manager to correct the scheme and then the match will happen.
  
 ===== How to save Override Pay Rates for future Timesheets for this Candidate/Vacancy combimation ===== ===== How to save Override Pay Rates for future Timesheets for this Candidate/Vacancy combimation =====
 +Schemes are set with the STANDARD rate of pay - what the Agency would prefer the candidate to be paid. However some candidates have custom rates of pay so the scheme needs to be overridden.
 +
 +Rather than having to overwrite manually every time (which is EVERY time if rate = 0.00) the Booking can have the override rates set in it to use in the future.
 +
 +From the timesheet view, use the **vacancy** button (opens in the shifts view). 
 +Click on a line containing the correct candidate's name. You may have to change the date back on the shift view to find the correct candidate.
 +
 +{{ :override_pay_rates..png?350|}}Click on the Booking/Rates view.\\ 
 +Go to the rates view (default)\\ 
 +Overwrite the pay rates (they will go red)\\
 +Save and refresh (background goes white to indicate an overwrite.)
 +
 +Now the timesheets on for this booking will always use these rates.
 +
 +===== How to Add Pay Lines =====
 +On the timesheet, use the **Add Rate** button. This will activate a new cell at the bottom of the existing lines.  Select the Pay Band and enter the units and rates.
 +
 +{{:add_rate_lineto_timesheet.jpg|}}
 +
 +**After completion you need to open the timesheet and add the shift date to the pay line** (You can only add a date of a shift linked to the timesheet. A dateless line is given with no date is given the last day of the week as a default so may need changed.)
 +
 +{{:shift_date_to_pay_line.jpg|}}
 +
 +===== Hours not equal ======
 +
 +{{ :hours_not_equal_warning.png?350|}}
 +Warning message when Sleep Over shifts exist.  This is because even though the sleepover covers HOURS only 1 UNIT is charged. Also the total cells are yellow. It is a warning to check a sleepover was intended.
 +
 +[[UG16-00|Audit Features]]
 +
  
  
 +Go back to [[3_quick_guides|Quick Guides/How To section]]